Shawver Project

 BLUEFEATHER Home

project home

Welcome,

First Consultation 2h Mon 10/4/04 Mon 10/4/04

Site Visit and Measurement 2h Mon 12/6/04 Mon 12/6/04

Enter Measurement into CAD 3.5h Sun 12/12/04 Sun 12/12/04

Second Consultation 3h Thu 12/16/04 Thu 12/16/04

Project Planning Phase 96d Thu 12/16/04 Thu 4/28/05

Outline Project Schedule 1d Thu 12/16/04 Thu 12/16/04

Space Planning 2w Thu 12/16/04 Wed 12/29/04

Concept Drawings 2w Thu 12/30/04 Wed 1/12/05

Schematic Drawings 4w Thu 1/13/05 Wed 2/9/05

Preliminary Cost Estimate 2d Thu 2/10/05 Fri 2/11/05

Construction Documents 36d Mon 2/14/05 Mon 4/4/05

Quality Specifications 1d Mon 2/14/05 Mon 2/14/05

Performance Specifications 2d Mon 2/14/05 Tue 2/15/05

Materials Specifications 21d Mon 2/14/05 Mon 3/14/05

Final Plans Drawings 14d Tue 3/15/05 Fri 4/1/05

Final Cost Estimate/Budget Established 1d Mon 4/4/05 Mon 4/4/05

Contractor Selection 13d Tue 4/5/05 Thu 4/21/05

Bid Out of Major Sub-Contractors 2w Tue 4/5/05 Mon 4/18/05

Selection of Sub-Contractors 1d Tue 4/19/05 Tue 4/19/05

Scheduling of Contractors 2d Wed 4/20/05 Thu 4/21/05

Ordering of Materials 2d Fri 4/22/05 Mon 4/25/05

Windows 1d Fri 4/22/05 Fri 4/22/05

Exterior Doors 1d Fri 4/22/05 Fri 4/22/05

Roof and Siding 1d Fri 4/22/05 Fri 4/22/05

Order Lumber Package 2d Fri 4/22/05 Mon 4/25/05

Order Roof Trusses 1d Fri 4/22/05 Fri 4/22/05

Order Drywall 1d Fri 4/22/05 Fri 4/22/05

Permitting 19d Mon 4/4/05 Thu 4/28/05

Submit Plans for City Review 14d Mon 4/4/05 Thu 4/21/05

Plan Revisions 5d Fri 4/22/05 Thu 4/28/05

Project Building Phase 113d Mon 5/30/05 Wed 11/2/05

Move Out Period 7d Mon 5/30/05 Tue 6/7/05

Staging 1d Wed 6/8/05 Wed 6/8/05

On-Site Dumpster 1d Wed 6/8/05 Wed 6/8/05

On-Site Toilet 1d Wed 6/8/05 Wed 6/8/05

Site Work Phase 20d Wed 6/8/05 Tue 7/5/05

Call for Locates 1d Wed 6/8/05 Wed 6/8/05

Excavation for New foundation and Utilities 5d Thu 6/9/05 Wed 6/15/05

Footings 3d Thu 6/16/05 Mon 6/20/05

Foundation 8d Tue 6/21/05 Thu 6/30/05

Backfill 2d Fri 7/1/05 Mon 7/4/05

Garage Slab 1d Tue 7/5/05 Tue 7/5/05

Demolition 38d Wed 6/8/05 Fri 7/29/05

Demolition and Gut Out of Interior Nest 1.5w Wed 6/8/05 Fri 6/17/05

Demolition and Gut Out of Exterior Nest 1w Wed 7/6/05 Tue 7/12/05

Demolition of Garage 2d Thu 6/9/05 Fri 6/10/05

Tear Off of Nest Roof 4d Tue 7/26/05 Fri 7/29/05

Framing 14d Wed 7/6/05 Mon 7/25/05

Garage Walls 2d Wed 7/6/05 Thu 7/7/05

Loft Floor 3d Fri 7/8/05 Tue 7/12/05

Loft Walls 4d Wed 7/13/05 Mon 7/18/05

Loft Roof 1w Tue 7/19/05 Mon 7/25/05

New Nest Walls 5d Wed 7/13/05 Tue 7/19/05

Roofing 2w Mon 8/1/05 Fri 8/12/05

Exterior Doors and Windows 3d Mon 8/15/05 Wed 8/17/05

Plumbing 43d Mon 8/15/05 Wed 10/12/05

Plumbing Rough In 8d Mon 8/15/05 Wed 8/24/05

Set Fixtures 3d Mon 10/10/05 Wed 10/12/05

Electrical 43d Mon 8/15/05 Wed 10/12/05

Electrical Rough In 8d Mon 8/15/05 Wed 8/24/05

Installation of Fixtures 3d Mon 10/10/05 Wed 10/12/05

HVAC 2w Mon 8/15/05 Fri 8/26/05

Insulation 1w Mon 8/29/05 Fri 9/2/05

Drywall 1.5w Mon 9/5/05 Wed 9/14/05

Painting 1.5w Wed 9/14/05 Fri 9/23/05

Trim and Millwork 28d Mon 9/26/05 Wed 11/2/05

Install Interior Doors 3d Mon 9/26/05 Wed 9/28/05

Millwork in Loft Office 3w Thu 9/29/05 Wed 10/19/05

Built In Cabinetry 2w Thu 9/29/05 Wed 10/12/05

Kitchen and Bathrooms 2w Mon 9/26/05 Fri 10/7/05

Flooring 2w Thu 10/20/05 Wed 11/2/05

 